It is week 20 and we are still moving along. The bathroom walls are completely tiled now. One of the three walls has the grout installed as well. We selected a color of grout that matched the neutral tones of the tile and we love how it blends them together.
The floor of the bathroom is also installed and is waiting for grout to be applied. We have decided to use the same color grout between the rocks on the ground and the tiles. This will help to blend the two different shapes together.
The countertop for the bathroom has been installed along with the sink. I can't wait to brush my teeth.
The big news in the kitchen is the installation of the countertops. They look great! This sink and the stove top have been installed as well and it's fun to pretend what it would be like to cook inside of the house. If you look closely you will notice that the countertops and cabinets are the same through out the house. We even had an extra piece of granite that we used for the base of the fireplace. We are ready to go and Jack is already sleeping in the house.