The back doors are in and we decided its time to show them off. The system can open up as a single door for simple in and out access or they can be folded completely open to create the indoor/outdoor experience. Very exciting!
Tuesday, August 18, 2015
Sunday, August 16, 2015
Week 11
- Meeting with architects and designers
- Picking out floor and ceiling tile
- Purchasing major appliances
- Reviewing work and discussing changes/modifications
- Shopping for various items like faucet handles and shower heads
- Designing and reviewing cabinets
- blah blah blah
Saturday, August 8, 2015
Week 10
Monday, August 3, 2015
Week 9
Michelle and I went to a store that sold slabs of rock for counter tops. We picked out a couple of our favorites and paid for them. Two men used a fork lift to move the slabs around the warehouse and spin them around so we could examine the surface. Each slab has a unique number. We purchased slab 12 and 13.
We are finalizing the design for the electrical work. We are creating a smart house with internet drops and Wi-Fi and a centralized av system. I was sketching out drawings with locations for special wiring on top of copies of our new layout
We are still working on the dirt jumps in the backyard. There are five rollers now and Benton is enjoying riding around the track.
Wednesday, July 29, 2015
Week 8
Week 8 and we are going strong. The electrician has started to put some of the wiring in. You can see where the ceiling lights will go. There are cables and wires hanging everywhere.
The water heater has been put in. We are going for a tankless water heater. It's going to look nice in the end because the box, which is in the wall, will have all of its plumbing hidden. This is possible because we are doing a complete remodel and not a retrofit. There is no need to be limited by existing plumbing.
Michelle and I spent the weekend pretending to relax on the new patio. Right now it is just a pile of rubble, but we spray painted where the steps will go and decided to make a couple minor adjustments to help with the flow.
We drove out to RCP block and brick today and purchased 610 used bricks. We will use the brick for our new walk way around the side of the house to the Ensenada garden. The bricks were a special find because they are used. They are match the other brick in the backyard that was made in the 1940's. Over the years brick colors and shapes have changed.
We recently purchased all of the appliances for the kitchen and the bathroom. This is a costly part of the project but exciting.
Michelle and I went shopping for bathroom tile on Sunday. We picked out some tile for the walls and the shower floor. We found some rocks that remind us of a surf spot in Mexico.
As usual, Jack is hanging out in the bushes and keeping an eye on things. Ryan, the person we are staying with, has decided to let me build his son a BMX track in the backyard so I am working on jumps every day and having fun in the sun.
GO SUMMER!
Sunday, July 19, 2015
Week 7
Cesar finished framing the back door a few days ago. They ripped everything out and built new walls and I am impressed with the work. They also blew out the wall into the bedroom and I thought they would frame it this weekend but they couldn't because of the weather. It has been hot and humid down here. Yesterday it rained all day. Today the clouds look threatening. It's Benton's birthday this weekend. Ryan and Camila bought him a new bicycle. It's green, just like the one I had in high school. My birthday present was a berm in the backyard. I hope Benton enjoys it when he comes home from his birthday party. Despite all the chaos in the backyard, Michelle flowers continue to bloom.